CompTIA Project+ (PK0-005) is an entry-level project management certification for people who coordinate or manage small and medium IT projects: project coordinators, junior project managers, team leads, business analysts and Scrum team members. Unlike PMP, it needs no formal project hours. It covers both waterfall and Agile, the project life cycle from discovery to closing, the tools and charts used to track work, and the IT basics a tech project manager must understand, such as security, compliance and change control.
This guide follows CompTIA's official Project+ page: the four domains with weights, the key terms and formulas, a 4-week plan and 15 original practice questions.
Quick facts (CompTIA, November 2026)
| Item | Detail |
|---|---|
| Exam code | PK0-005 (V5), launched 8 November 2022 |
| Questions | Maximum 90, multiple choice and performance-based |
| Duration | 90 minutes |
| Passing score | 710 on a 100–900 scale |
| Languages | English, Japanese, Thai |
| Recommended experience | 6–12 months of hands-on experience managing projects in a tech environment |
CompTIA usually replaces an exam about three years after launch. At the time of writing its page still lists PK0-005 and no successor, so check the official CompTIA Project+ page for the current version before you buy a voucher.
Domains and weights
| Domain | Weight | Key topics (from CompTIA) |
|---|---|---|
| Project Management Concepts | 33% | Project characteristics and methodologies; Agile vs waterfall; change control; risk, issue, schedule, quality, communication, meeting, team and resource management; procurement and vendor selection |
| Project Life Cycle Phases | 30% | Discovery artefacts; initiation; planning; execution; closing |
| Tools and Documentation | 19% | Project tools; productivity tools; quality and performance charts |
| Basics of IT and Governance | 18% | Environmental, social and governance (ESG); information security; compliance and privacy; IT concepts; change control |
The life cycle at a glance
| Phase | Main outputs |
|---|---|
| Discovery / concept | Business case, feasibility, pre-project budget estimate, initial requirements |
| Initiation | Project charter, stakeholder register, high-level scope, sponsor approval |
| Planning | Scope statement, work breakdown structure (WBS), schedule, budget, risk register, communication plan, RACI |
| Execution | Deliverables, status reports, change requests, issue log, quality checks |
| Closing | Customer sign-off, release of resources, lessons learned, archived documents, closed contracts |
Waterfall vs Agile
| Waterfall | Agile (Scrum) |
|---|---|
| Scope fixed early; changes go through formal change control | Scope evolves through a prioritised product backlog |
| Delivers once, at the end | Delivers working increments every sprint (usually 1–4 weeks) |
| Roles: project manager, sponsor, team | Roles: product owner, Scrum master, development team |
| Fits fixed-requirement work such as a data-centre move | Fits products whose requirements will change, such as a new app |
Know the Scrum events (sprint planning, daily stand-up, sprint review, retrospective), Kanban boards and WIP limits, and terms such as user stories, velocity and burndown charts.
Charts and formulas
- Gantt chart: tasks over time with dependencies; critical path = the longest chain of dependent tasks, which sets the shortest possible duration. Tasks on it have zero float.
- Burndown chart: remaining work per sprint; a flat line means the team is stuck.
- Pareto chart: the few causes behind most defects (80/20). Fishbone (Ishikawa): root causes of one problem. Scatter and histogram charts show relationships and distributions.
- Earned value: SPI = EV ÷ PV and CPI = EV ÷ AC. Below 1 means behind schedule or over budget. Example: EV ₹4 lakh, AC ₹5 lakh gives CPI 0.8, so the project is over budget.
- Communication channels: n(n − 1) ÷ 2. A team of 6 has 15 channels; adding a 7th person makes 21.
4-week study plan
| Week | Focus | Practice |
|---|---|---|
| 1 | Concepts: methodologies, Agile vs waterfall, risk and issue management, change control, communication | Write a risk register with five risks and a response for each |
| 2 | Life cycle: charter, scope, WBS, schedule, budget, execution and closing | Create a charter and WBS for a small IT project (for example, an office Wi-Fi upgrade) |
| 3 | Tools and charts: Gantt, critical path, burndown, Pareto, fishbone; earned value; RACI | Build a Gantt chart and find the critical path; do 20 EV calculations |
| 4 | IT basics and governance: security, privacy, compliance, ESG, IT change control; mocks | Two timed mocks; book the exam |
15 practice questions with answers
These are original questions written for this guide, not exam questions.
1. Which document formally authorises a project and names the project manager?
The project charter.
2. A stakeholder asks for a new feature halfway through a waterfall project. What is the first step?
Log a change request and assess its impact on scope, schedule, cost and risk before the change control board decides.
3. Which tool breaks the scope into smaller, manageable deliverables?
The work breakdown structure (WBS).
4. A task on the critical path slips by two days. What happens to the project end date?
It slips by two days, unless the schedule is compressed (crashing or fast-tracking).
5. EV is ₹6 lakh and PV is ₹8 lakh. Is the project ahead or behind schedule?
Behind: SPI = 0.75.
6. How many communication channels does a 10-person team have?
45.
7. Which chart shows which few causes produce most of the defects?
A Pareto chart.
8. A risk has been identified but not yet happened. Where is it tracked? Once it happens, where does it go?
The risk register; once it happens it becomes an issue in the issue log.
9. You buy insurance against a vendor failing to deliver. Which risk response is this?
Transfer.
10. Who prioritises the product backlog in Scrum?
The product owner.
11. What meeting happens at the end of each sprint to improve how the team works?
The sprint retrospective.
12. Which matrix shows who is Responsible, Accountable, Consulted and Informed for each task?
A RACI matrix.
13. A project will store customer personal data. Which governance area must the plan cover?
Compliance and privacy (data protection law, such as India's DPDP Act, 2023), plus information security controls.
14. What must happen before releasing the team at project closing?
Customer acceptance or sign-off of deliverables, then lessons learned and closing contracts.
15. A server change will cause downtime. Which process approves it and schedules the maintenance window?
IT change control (the change advisory board).
After Project+
- Add technical depth with AZ-900 or AWS Cloud Practitioner so you can run cloud projects with confidence.
- For QA-heavy projects, see ISTQB CTFL.
- Browse the best IT certifications for freshers and live IT jobs.
Cloud Soft Solutions in Ameerpet, Hyderabad trains freshers and working professionals in cloud, DevOps and AI with real-time projects run the way IT teams run them. See the APEX program and all courses.
📞 Call +91 96660 19191 · WhatsApp · Flat No. 513, 5th Floor, Nilagiri Block, Aditya Enclave, Ameerpet, Hyderabad
Frequently Asked Questions
What is the current CompTIA Project+ exam code?
PK0-005, launched on 8 November 2022. Check comptia.org for any newer version before buying a voucher.
How long is the Project+ exam?
90 minutes, with a maximum of 90 multiple-choice and performance-based questions.
What is the Project+ passing score?
710 on a 100–900 scale.
Do I need project experience for Project+?
No formal hours are required. CompTIA recommends 6–12 months of hands-on experience managing projects in a tech environment.
Which Project+ domain has the most weight?
Project Management Concepts at 33%, followed by Project Life Cycle Phases at 30%.
Does Project+ cover Agile?
Yes. Agile vs waterfall and Agile practices are part of the Project Management Concepts domain.